Skip to main content

Solar calculator

Everything starts in the simulator: type your consumption or take it from your bill or the map, and watch the financial model live.

1How much electricity do you use?

Or take it, more precisely, from:

2How big should the plant be?

System size4.8 kWp

Recommended from your consumption

That size means 8 panels and about 29 m² of roof.

3How will you pay?

Loan share of project cost68%

Annual interest 14% — per the referenced financing scheme.

A 4.8 kW plant would earn you about 46 million toman in its first year and pay for itself in about 9.9 years.

Project cost

497 million toman

Down payment: 159 million toman

Monthly instalment

7.9 million toman

Repaid over 60 months

Payback period

9.9 years

From the cumulative cash flow

System size

4.8 kWp

8 panels · ~29 m²

Year-one production

7,900 kWh per year

Year-one income: 46 million toman

25-year net profit

2.9 billion toman

After costs, inverter replacement and instalments

Return on investment

1,805%

IRR: 16%

These figures are a simulation. For the formal assessment sheet — with price ranges and a plant proposal — complete the assessment.

25-year cash flow

Bars: yearly net · line: cumulative · dashed: payback

Monthly production (year one)

Three scenarios

Selected scenario: project cost 497 million toman · year-one income 46 million toman

Cash versus financing

CashFinancing
Initial investment497 million toman159 million toman
Monthly instalment7.9 million toman
Total interest134 million toman
Payback8.4 years9.9 years
25-year net profit3 billion toman2.9 billion toman
Return on investment605%1,805%
Year-by-year financial modelopen for the full table
YearProductionRevenueCostsLoanNetCumulative
17,90046 million toman5 million toman94 million toman−53 million toman−212 million toman
27,90051 million toman5.5 million toman94 million toman−49 million toman−261 million toman
37,80055 million toman6 million toman94 million toman−45 million toman−306 million toman
47,80061 million toman6.6 million toman94 million toman−40 million toman−346 million toman
57,70066 million toman7.3 million toman94 million toman−35 million toman−382 million toman
67,70072 million toman8 million toman64 million toman−317 million toman
77,60079 million toman8.8 million toman70 million toman−247 million toman
87,60087 million toman9.7 million toman77 million toman−170 million toman
97,50095 million toman11 million toman84 million toman−86 million toman
107,500104 million toman12 million toman92 million toman6.1 million toman
117,500113 million toman13 million toman100 million toman106 million toman
127,400124 million toman156 million toman−32 million toman74 million toman
137,400135 million toman16 million toman120 million toman194 million toman
147,300148 million toman17 million toman131 million toman325 million toman
157,300162 million toman19 million toman143 million toman468 million toman
167,200177 million toman21 million toman156 million toman624 million toman
177,200193 million toman23 million toman171 million toman795 million toman
187,100212 million toman25 million toman186 million toman981 million toman
197,100231 million toman28 million toman204 million toman1.2 billion toman
207,100253 million toman30 million toman223 million toman1.4 billion toman
217,000277 million toman33 million toman243 million toman1.7 billion toman
227,000302 million toman37 million toman266 million toman1.9 billion toman
236,900331 million toman40 million toman290 million toman2.2 billion toman
246,900361 million toman44 million toman317 million toman2.5 billion toman
256,900395 million toman49 million toman346 million toman2.9 billion toman
Calculation assumptions
Specific yield (net of losses)
1,650 kWh/kWp·yr
Guaranteed purchase per kWh
5,854 toman
Annual purchase-price growth
10%
Annual panel degradation
0.6%
Annual O&M (of project cost)
1%
Inverter replacement
Year 12 — 10% of project cost
Financing
14% annual interest
Discount rate (NPV)
15%
Net present value (NPV)
19 million toman
Project lifetime
25 years
Assumptions version
invest-market-anchor-1405.05

These results are approximate estimates from the stated assumptions, not a promise of return. Final system size, equipment prices and connection terms are confirmed after technical assessment and a site visit.

Project cost497 million toman

Monthly instalment7.9 million toman

Payback period9.9 years